The maintenance procedure for the aerodynamic cut-off valves includes the following steps:
I. Preparatory work:
Close the valves and associated equipment to ensure the safety of the work area and to prepare the tools and materials required.
Dismantling valve cap:
Use the appropriate tools to screw the pine valve bolt and remove the lid from the valve.
Dismantling valve cores:
Unlock the threads of the valve core and take it off.
Dismantling seals:
Take off the seal on the core of the valve and check for wear or tear, if necessary, for replacement.
Cleaning valves and cores:
Cleaning valves and cores with detergents and brushes to ensure that the surface is clean.
Check valves and valve cores:
Carefully examine whether the valves and cores have cracks, wear or other damage, and if necessary repair or replacement.
VII. Replacement of seals:
Seals on valve cores shall be replaced as necessary to ensure normal sealing.
Reassembly valve core:
The core is placed back into the valve to ensure that the screws are firm.
IX. Installation of valves:
Purge clean valve caps and reset them with bolts.
10. Test valves:
Open the relevant equipment, perform leak tests and performance tests to ensure that valves work properly.
XI. Areas of clearance:
Clear the area of work to ensure that there are no remaining tools or materials.